The Solution
The Haye’s facility has been engineered from the ground up with scalability in mind; a modular approach will enable Enel X to seamlessly expand the existing infrastructure to accommodate a fleet of up to 56 electric buses.
Working as part of the ENEL X Ebus team, Cleaner EV Ltd were responsible for enabling the site’s electrical infrastructure for e-bus charging, installing a low voltage switch panel and switch gear that now powers six 300Kw Enel X Way charging stations.
Connection to the grid was supported by ESP utilities Group, via 11Kv substation providing a 2,000Kva capacity for the bus depot.
Abellio bus depots utilise 382 kWh batteries what can be charged to full capacity in a little over 3 hours.